Reorder Point Formula: When Should You Buy More Stock?
Work out when to reorder stock using daily demand, supplier lead time and a practical buffer. Includes a small-business example and common mistakes.
Product guide from the team behind OrderTracker. Examples are illustrative, not customer results.
A basic reorder point is average daily demand multiplied by replenishment lead time, plus safety stock. Use consistent units and days, then check committed orders and outstanding supplier orders before buying more. The result tells you when to review replenishment, not automatically how much to buy.
Finding an empty shelf is a poor reminder to reorder. By then, the customer is waiting and your supplier's usual delivery time suddenly feels much longer.
You do not need a complicated forecast to improve that situation. Start with one item that regularly interrupts your work: a blank T-shirt size, a packaging box or a material you use on most jobs. Work out a sensible warning level, then review whether it is doing its job.
What is a reorder point?
A reorder point is the stock level that tells you to review buying more before the next delivery is needed. It is different from the reorder quantity, which is the amount you decide to buy.
The basic formula is:
Reorder point = (average daily demand × replenishment lead time in days) + safety stock
This is the standard calculation described in Shopify's reorder-point guide. It is a starting point. If demand swings sharply or a supplier is unreliable, the inputs need more attention than the arithmetic.
A simple example you can check yourself
Suppose your shop used 120 small mailer boxes over 30 calendar days. Your supplier normally takes seven calendar days from order placement to usable delivery. You decide to keep 12 extra boxes as an initial buffer.
| Step | Calculation | Result |
|---|---|---|
| Average daily use | 120 boxes ÷ 30 days | 4 boxes per day |
| Use while waiting | 4 × 7 days | 28 boxes |
| Add the chosen buffer | 28 + 12 | 40 boxes |
In this illustrative example, 40 boxes is your review point. It is not a recommendation to buy 40 boxes. If the supplier sells cases of 100, you still need to decide whether a case fits your upcoming work, storage space and cash budget.
Use the same units all the way through
Count boxes as boxes, not sometimes as cases and sometimes as individual pieces. If a case holds 100, convert it before comparing it with daily usage. Give different sizes separate records; spare large mailers do not necessarily replace the small ones you need.
Be equally careful with days. Four boxes per calendar day multiplied by seven calendar days is consistent. Four boxes per working day multiplied by a seven-calendar-day delivery estimate may not be. Choose one basis and document it.
For materials, use consumption rather than finished-product sales. A job selling one custom gift set might consume a box, two inserts and three labels. Counting that as one label of demand would give you a misleading warning level.
Measure the wait until stock is actually usable
Lead time starts when you place the replenishment order and ends when you can use the goods. Include supplier preparation, transit and your receiving check. “Ships in two days” is not the same as “ready on your shelf in two days.”
Look at several recent deliveries instead of relying on a remembered best-case arrival. If a holiday closure is coming up, check it with the supplier before accepting new work. Record a longer planning allowance when you have a specific reason for it.
How much safety stock should you keep?
There is no useful universal percentage for every small shop. A low-cost box that fits nearly every order is a different decision from an expensive, personalized component that may never be used again.
For your first review, write down the interruption you are trying to cover. In our example, 12 boxes cover three additional days at the assumed average use. Ask whether that is enough for the delays you actually encounter. Then compare the buffer with actual usage and arrivals over the following weeks.
Do not describe the buffer as guaranteed protection. A sudden large order, damaged delivery or extended supplier delay can still exhaust it. For a seasonal product, use a relevant demand period rather than a quiet annual average.
Check reservations and open purchase orders before reordering
The number physically on the shelf may already belong to accepted work. On the other hand, an order you placed yesterday may already be on its way. Looking at only one of those facts can lead to a shortage or an unnecessary second purchase.
- Confirm the physical stock count if the number looks wrong.
- Check quantities committed to accepted customer orders.
- Review supplier orders already placed, including expected arrival dates.
- Compare the stock available before that arrival with work due before it.
- Record the replenishment decision so someone else does not duplicate it.
A reservation-based available-stock figure has already removed committed quantities. Do not subtract those same commitments a second time. Likewise, avoid treating stock due next month as available for a job due tomorrow.
Set a practical warning level in OrderTracker
For a tracked product, enter the low-stock threshold you have chosen and keep the stock count current. OrderTracker's stock reminders compare on-hand stock minus reservations with that threshold. They flag a review; they do not calculate your supplier lead time or buy stock for you.
Because that comparison uses available stock, understand how you use reservations before copying a conventional reorder formula into the field. If the demand in your calculation already includes reserved jobs, check that you are not allowing for the same work twice. Start with a small, documented example and adjust the warning level to your workflow.
Use the on-hand, reserved and available stock guide to check the quantities, then review your open purchases using the purchase-order and partial-delivery workflow. One well-maintained warning level is more useful than twenty copied numbers nobody understands.
Common questions
Is a reorder point the same as safety stock?
No. Safety stock is the extra buffer. The basic reorder point includes expected demand during replenishment lead time plus that buffer.
How often should I review my reorder point?
Review it when demand, supplier timing, pack sizes or your commitments change. A short weekly check is a practical starting routine for fast-moving items.
Does a low-stock alert automatically order from my supplier?
No. In OrderTracker it is an in-app reminder to review stock. You decide what to buy and place the supplier order through your normal purchasing process.